Construction of Multi-Use Pathways, Sidewalks and Pathway Renewals COW#241-2016
Building and Renewing Pathways in South East and South West Winnipeg
Type of Service: Pathway and Sidewalk Construction, Aggregate Crushing, Asphalt Paving
Client: City of Winnipeg
Location: City of Winnipeg, multiple locations
Year: 2016
Contract Value: $ 728,585.91
Project Overview: Multi-Use Pathway Renewals, New Pathway and Sidewalk Construction
Scope of work:
- (i) Excavation
- (ii) Sub-Grade Compaction
- (iii) Crushed Sub-base Material
- (iv) Supplying and Placing Base Course
- (v) Supplying and Placing “A” Base – Base Course
- (vi) Asphalt Pavement Removal
- (vii) Construction of Type 1A Asphalt Overlay
- (viii) Sidewalk Renewal
- (ix) Supply and Install of Corrugated Steel Culverts
- In addition Part B components:
- 1. Ditch Excavation
- 2. Ditch Grading
- 3. Concrete Curb Removal
- 4. Construction of 40mm Lip Curb
- 5. Concrete Curb Renewal
- 6. Planing of Asphalt
- 7. Construction of 100 mm Sidewalk
- 8. Construction of Type 1A Asphalt Pavement
- 9. Adjustment of Catchbasins/Manholes
- 10. Chain Link Fence
- In addition Part C components:
- 1. 150 mm Concrete Partial Slab Patches
- 2. 150 mm Sidewalk Renewal
- 3. Concrete Curb Renewal
- 4. Construction of 40 mm Curb and Gutter Lip Curb
- 5. Construction of Curb Ramp
- 6. Construction of 100 mm Concrete Sidewalk
- 7. Replacing Manhole and Catchbasin Frames and Covers
- 8. Adjustment of Catchbasins/Manholes
- 9. Adjustment of Valve Boxes
- (x) Seeding and sodding