Project Overview
The work consisted of Phase 1 Bridgwater subdivision site remediation in preparation for further development, including: removal of structures on site, excavation of 250,000m3 of mud and debris from the decommissioned landfill and construction of berms onsite.
Scope of Work:
- Excavation
- Removal and Disposal of contaminated soil
- Backfill
- Berm construction